Contractor Brief

Electrical & Plumbing —
First Fix to Final Finish

Pool Ground Floor Office — Stayezy, Chithirapuram, Munnar

Complete MEP work for a 45 sq.m luxury office space located below a figure-8 infinity pool. The interior features dark marble walls, brushed gold accents, and warm LED lighting throughout. Floor and pump room are ready. We need to begin first-fix immediately.

~0
Total Electrical Points
0
Light Points
0
Switches & Sockets
0
Power Circuits
0
Washrooms
0
Work Phases
Scope of Work

Work Phases

6 phases from first fix to final handover

Floor ready, pump room done. Begin immediately.

Electrical Rough-In

  • Run concealed PVC conduit (20mm) in all walls and ceiling for every point
  • Pull cables: 4 sq.mm for AC/pump, 2.5 sq.mm for sockets, 1.5 sq.mm for lights
  • Run Cat6 cable for 4 data points and 3 CCTV cameras
  • Install 40 GI mounting boxes at all switch and socket locations
  • Route conduits from DB board (back wall behind reception) to every point
  • Mark all 11 pendant hook points on ceiling slab
  • Mark all 24 downlight positions on ceiling slab

Plumbing Rough-In

  • Cold water supply lines to both WCs (left + right on back wall)
  • Hot water supply to both basins (if instant heater planned)
  • Install concealed cistern frames for 2 wall-mounted WCs
  • Run 110mm soil pipe along back wall connecting both WCs to main soil stack
  • Run 50mm waste pipes for 2 basins with P-trap
  • Install 2 floor drains with traps
  • Isolation valves for each WC
  • All drain pipes minimum 1:40 slope

Glass Door Track Recesses

  • Get exact bottom track dimensions from glass vendor
  • Set 6 track recesses in floor before any tiling
  • Bay widths: 3340, 4160, 2730, 2330, 3450, 2380 mm

AC Piping

  • Copper piping for 2 ACs: reception (2 ton) + manager (1.5 ton)
  • AC condensate drain to nearest drain point
  • Insulate all copper pipes
Critical Notes

Electrician and plumber coordinate — both share the back wall

LED strip channels plan now, install in Phase 3

No plastering or tiling until rough-in verified and photographed

Scope of Work

  • Build WC partition walls — both 2700 × 1200mm on back wall
  • Waterproofing both WC floors and walls (Dr. Fixit or equivalent)
  • Water ponding test 24 hours — zero leaks before proceeding
  • Plaster and render all walls
  • Manager cabin partition if required
  • Verify all conduit and pipe positions before closing walls

Ceiling Framework

  • GI frame for false ceiling all areas
  • Cutouts for 24 downlight positions
  • Zones for wood slat panel mounting

Second Fix Electrical

  • Pull all wiring through conduits
  • Install LED strip aluminium channels with diffusers: Reception ceiling cove (~6m), Manager ceiling cove (~4m), Reception back wall logo (~3m), Reception desk underside (~3.5m), Manager shelves (2 runs ~6m), Manager desk underside (~2m), WC left mirror+vanity+niche (3 runs), WC right mirror+vanity+niche (3 runs)
  • Install 6 LED drivers behind ceiling (1 per zone)
  • Wire all switch/socket boxes
  • Wire CCTV Cat6 to cameras and NVR
Critical Notes

LED channels MUST install now. Cannot add after gypsum board closes ceiling.

Scope of Work

  • Dark marble flooring throughout (leave glass track recesses clean)
  • WC wall marble/tiles — full dark marble
  • Reception back wall marble cladding
  • Manager cabin marble cladding
  • Vanity counter marble with basin cutout both WCs
  • Grout and polish
  • Verify glass door track recesses unobstructed
Critical Notes

Order marble from same lot for consistent veining. Lead time 2–4 weeks — order during Phase 1.

Carpentry

  • Wood slat paneling reception back wall
  • Wood slat storage cabinets both WCs
  • Reception counter (dark marble + gold wave accent)
  • Manager desk (dark marble + gold legs)
  • Backlit display shelves manager cabin

Glass Doors

  • Install tracks, panels, hardware for all 6 bays
  • 4 curved + 2 straight, total 18.39m
  • Seal and weatherproof all joints

Metalwork

  • Gold accent trim on reception counter
  • Gold vanity fronts both WCs
  • Gold accent on manager desk
  • Stayezy logo letters (gold, backlit)

Electrical Final Fix

  • Close ceiling with gypsum + paint
  • Install 11 pendant lights
  • Install 24 downlights
  • Connect and test 12 LED strip runs
  • Install all switches and sockets: 2× 4-gang black, 3× 2-gang black, 2× 1-gang exhaust black, 1× 1-gang white pump, 2× dimmer black, 1× master switch black, 2× USB-C module black, 6× 5A twin black, 1× 5A single black, 1× 5A twin white, 2× 5A IP44 white, 3× 15A black, 2× 15A IP44 white, 2× 16A weatherproof grey, 4× RJ45 Cat6 black, 2× 20A DP isolator
  • Install DB board with labelled MCBs
  • Install 3 CCTV cameras + NVR
  • Install 2 exhaust fans (150mm IP44)
  • Install 2 smoke detectors + 1 emergency light + doorbell
  • Test all circuits, dimmers, master switch
  • Earthing test + RCCB trip test

Plumbing Final Fix

  • Install 2 wall-mounted WCs + concealed flush plates
  • Install 2 basins with mixer taps (black/gold finish)
  • Connect and test all supply lines
  • Flow test and leak check
  • Install LED-backlit mirrors both WCs
  • Install accessories (towel rail, soap dispenser — black/gold)

Final

  • Install Stayezy logo with LED backlight
  • Install AC indoor units and commission
  • Furniture, plants, decor
  • Final clean and handover
Technical

Circuit Schedule

Distribution board layout — 16-way flush mount

CircuitDescriptionMCBCableLoad
C1Lighting Reception + Lounge10A SP1.5mm²Pendants + downlights + LED
C2Lighting Manager cabin10A SP1.5mm²Pendants + downlights + LED
C3Lighting WC left + right6A SP1.5mm²Pendants + downlights + LED
C4Sockets Reception + Lounge16A SP2.5mm²5A + 15A sockets
C5Sockets Manager cabin16A SP2.5mm²5A + 15A sockets
C6Sockets WCs + Back wall16A SP2.5mm²WC + utility
C7CCTV + Data6A SP1.5mm²NVR + PoE
C8Exhaust fans6A SP1.5mm²2 fans
PC-1AC Reception 2 ton32A DP4mm²Dedicated
PC-2AC Manager 1.5 ton32A DP4mm²Dedicated
PC-3Pump room32A DP4mm²Dedicated
PC-4Vending machine20A DP2.5mm²Dedicated
C9–C11Spare (3 circuits)10–16AFuture
MAINIncoming isolator63A DP10mm²
RCCBEarth leakage63A 30mAFull board
Layout

Floor Plan

Pool ground floor office — 45 sq.m

Floor Plan — Pool Ground Floor Office, 45 sq.m

Pool Ground Floor Office — 45 sq.m | Click to view full size

Drawing

Electrical Layout Drawing

Complete electrical point layout for the ground floor office

Electrical Layout Plan — Drawing No: EL-GF-01 Rev.2

Electrical Layout Plan — Drawing No: EL-GF-01 Rev.2 | All points, circuits, and positions marked

Vision

Design References

All installations must support these finishes. Concealed work throughout.

🏛

Reception

Dark marble counter, Stayezy logo, gold accent, pendant lights

💼

Manager Cabin

Marble desk, gold legs, backlit display shelves, warm LED

🚿

Washrooms

Dark marble walls, LED-backlit mirrors, gold vanity, IP44 fixtures

Important

Key Notes

1.All WC items IP44 rated
2.LED strip channels route in ceiling framework BEFORE gypsum
3.Switches and sockets: normal black modular
4.Lights: warm white 3000K, dimmable in reception + manager
5.CCTV: PoE via Cat6, no separate power cable
6.AC outdoor: external wall, 16A weatherproof socket
7.DB: 16-way flush mount, all circuits labelled
8.Earthing: building earth pit, separate earth for AC + data
9.Glass track recesses: get vendor dimensions before floor work
10.AC isolators within 1m of indoor unit
11.Electrician + plumber coordinate on back wall routing
12.Photograph all concealed work before closing
13.Marble same lot — order during Phase 1, 2–4 week lead time
14.Waterproofing ponding test mandatory before WC tiling